Managing Change in Scrum
While the whole reason for adopting Agile is to allow for flexibility in design during a project, there is a balance between refining the product concept and change for the sake of change. In order to strike this balance, there is a change management process. The need for change can be caused by a variety of internal and external factors, such as:-
- changes to legislation that affect the product design (external)
- news of a competitor product (external)
- Changes in budget (internal)
- Tweaks to product based on deliverables to date (internal)
The change is formalised via a change request document. The format or content for the Change Request, is suggested to be similar to a change/scope change request for a traditional projec. This is because the requirements must be changed if the change is accepted. In a traditional project, this applies to the Requirements Document. In a Scrum, the changes must be applied to the Product Backlog.
Recommended Further Reading
The following materials may assist you in order to get the most out of this course:
Course Contents
Section 1: Agile Project Management
Section 2: Using the Agile Manifesto to Deliver Change
Section 3: The 12 Agile Principles
Section 4: The Agile Fundamentals
Section 5: The Declaration of Interdependence
Section 6: Agile Development Frameworks
Section 7: Introduction to Scrum
Section 8: Scrum Projects
Section 9: Scrum Project Roles
Section 10: Meet the Scrum Team
Section 11: Building the Scrum Team
Section 12: Scrum in Projects, Programs & Portfolios
Section 13: How to Manage an Agile Project
Section 14: Leadership Styles
Section 15: The Agile Project Life-cycle
Section 16: Business Justification with Agile
Section 17: Calculating the Benefits With Agile
Section 18: Quality in Agile
Section 19: Acceptance Criteria and the Prioritised Product Backlog
Section 20: Quality Management in Scrum
Section 21: Change in Scrum
Section 22: Integrating Change in Scrum
Section 23: Managing Change in Scrum
Section 24: Risk in Scrum
Section 25: Risk Assessment Techniques
Section 26: Initiating an Agile Project
Section 27: Forming the Scrum Team
Section 28: Epics and Personas
Section 29: Creating the Prioritised Product Backlog
Section 30: Conduct Release Planning
Section 31: The Project Business Case
Section 32: Planning in Scrum
Section 33: Scrum Boards
Section 34: Sprint Planning
Section 35: User Stories
Section 36: User Stories and Tasks
Section 37: The Sprint Backlog
Section 38: Implementation of Scrum
Section 39: The Daily Scrum
Section 40: The Product Backlog
Section 41: Scrum Charts
Section 42: Review and Retrospective
Section 43: Scrum of Scrums
Section 44: Validating a Sprint
Section 45: Retrospective Sprint
Section 46: Releasing the Product
Section 47: Project Retrospective
Section 48: The Communication Plan
Section 49: Formal Business Sign-off
Section 50: Scaling Scrum
Section 51: Stakeholders
Section 52: Programs and Portfolios