Back

Processes that are Most Likely to Change

Although Scrum is iterative, not all the processes are iterative, so there is no opportunity to change them within a project, although the learnings from the project can be taken and applied to any subsequent projects. The iterative processes can be subject to change and improvement as the project progresses. Let’s look at the high level process/value chain.

“Initiate” and “Release” are not iterative as they precede and follow the sprints. “Plan and Estimate”, “Implement” and “Review and Retrospect” are iterative and it is possible to improve these processes as the project progresses.

When Can a Process Change be Identified?

Agile, and Scrum as an Agile method, welcomes change, but at the right time. Changes to a product can be requested at any time by a stakeholder, but will only be considered at the end of a sprint. A similar approach should be taken with process change – it should only be applied before the next sprint starts. The exception here could be if there is a roadblock of some nature that is interrupting the process. This is something the Scrum Master mitigates immediately, so that the process flow can resume. This may not necessarily be a process change, but it could be. For instance, if the Product Owner is not available for the next sprint meeting, it cannot be held without him – some business rules could be applied to avoid this happening in future.

Although the need to tweak a process can be raised at any time, for instance during the daily standup meeting, there is an ideal forum for discussing and ratifying the change, and that is during the Sprint Retrospective. This is where all the activities that took place during the sprint are reviewed as to whether they went well or could be improved. Where an improvement is required, this is the meeting where the process change can be discussed an agreed. As mentioned before, the Scrum Master is the process owner, and while he should not impose a change, he can argue for the change on the basis of his Scrum knowledge. This is when he will need to be diplomatic and win over the team with a reasoned explanation as to why the change would be beneficial. Once a consensus is reached that a change to the process should be applied, this is documented in preparation for the next sprint.

Recommended Further Reading

The following materials may assist you in order to get the most out of this course:

Section 2: Using the Agile Manifesto to Deliver Change

Section 3: The 12 Agile Principles

Section 4: The Agile Fundamentals

Section 5: The Declaration of Interdependence

Section 6: Agile Development Frameworks

Section 7: Introduction to Scrum

Section 8: Scrum Projects

Section 9: Scrum Project Roles

Section 10: Meet the Scrum Team

Section 11: Building the Scrum Team

Section 12: Scrum in Projects, Programs & Portfolios

Section 13: How to Manage an Agile Project

Section 14: Leadership Styles

Section 15: The Agile Project Life-cycle

Section 16: Business Justification with Agile

Section 17: Calculating the Benefits With Agile

Section 18: Quality in Agile

Section 19: Acceptance Criteria and the Prioritised Product Backlog

Section 20: Quality Management in Scrum

Section 21: Change in Scrum

Section 22: Integrating Change in Scrum

Section 23: Managing Change in Scrum

Section 24: Risk in Scrum

Section 25: Risk Assessment Techniques

Section 26: Initiating an Agile Project

Section 27: Forming the Scrum Team

Section 28: Epics and Personas

Section 29: Creating the Prioritised Product Backlog

Section 30: Conduct Release Planning

Section 31: The Project Business Case

Section 32: Planning in Scrum

Section 33: Scrum Boards

Section 34: Sprint Planning

Section 35: User Stories

Section 36: User Stories and Tasks

Section 37: The Sprint Backlog

Section 38: Implementation of Scrum

Section 39: The Daily Scrum

Section 40: The Product Backlog

Section 41: Scrum Charts

Section 42: Review and Retrospective

Section 43: Scrum of Scrums

Section 44: Validating a Sprint

Section 45: Retrospective Sprint

Section 46: Releasing the Product

Section 47: Project Retrospective

Section 48: The Communication Plan

Section 49: Formal Business Sign-off

Section 50: Scaling Scrum

Section 51: Stakeholders

Section 52: Programs and Portfolios

Translate »